Projects
Important Projects Portfolio as on January-2023
| A. Turn-key Works Completed for Major Ports | ||||
| Sl. No. | Name of Project | Port | Track Km | Cost in INR Cr. |
| 1 | Modernization and up-gradation of the existing railway network | SMP | 3.8 | 9 |
| 2 | Laying of new railway track at west of western yard I and laying paving block loading Platform | ChPT | 3.6 | 13 |
| 3 | Up-gradation of Platform no.2 & 3 in the Port Marshalling yard | NMPT | 3.5 | 7 |
| 4 | Up-gradation of Railway Line 1 & 2 | |||
| 5 | Rail Connectivity to 4th Terminal being developed by BMCTPL (PSA) | JNPA | 3.1 | 41 |
| 6 | Upgradation of the Track Nos. 10,12,14,16,18,19,20,21,22 | SMP | 12 | 38.2 |
| and 23 at EJC yard | ||||
| 7 | Accommodate full rake length at 7 Netaji Subhash Dock and its yard under KDS, KoPT | SMP | 1.7 | 18 |
| 8 | Providing direct connection between OEC and Western sector | VPA | 1 | 22.55 |
| joining at NAD curve from E.Co. Railway | ||||
| 9 | Connection of dead- end line at North of R& D yard to Eastern | VPA | 1.5 | 15.14 |
| Grid (Third line) from East Coast Railways | ||||
| 10 | Additional work of providing 3rd line near 14 lever goomty at NH yard | VPA | 0.9 | 2.41 |
| 11 | Rail connectivity to berth No. 13, 14, 15 & 16 from take-off point to west end of berth Phase-1: Ground Improvement by Stone Column | DPA | 4.15 | 73.5 |
| 12 | Rail connectivity to berth No. 13, 14, 15 & 16 from take-off point to west end of berth Phase-2: Bridge and Track Linking Work | DPA | 6.9 | 28.86 |
| 13 | Construction and Commissioning of new port Rail yard with rail connectivity between Marshalling yard and Hare island | VoCPA | 12 | 53 |
| 14 | Design supply erection testing & Commissioning 25 KV, 50 Hz single phase traction Over Head Equipment and other associated modification work of Rd no. 6 and 7 in the Haldia dock complex | HDC | 4.15 | 2.1 |
| 15 | Extension of line No. 11 to 15 to full length at R&D yard | VPA | 1.5 | 13.39 |
| 16 | Supply of PSC sleepers and carting of sleepers from | PPA | _ | 11.92 |
| Dhanmandal Station of Eco Rly to PPT | ||||
| 17 | Track Renovation including other related ancillaries Civil work in SMP Yard | SMP | 2.7 | 15.1 |
| 18 | Doubling of Railway line from Durga Chak to Haldia Dock | HDC | 7 | 99.37 |
| 19 | Upgradation of rail network inside Cargo jetty – Civil and P. way Work | DPA | 13 | 45.51 |
| 20 | ONGC Bridge Extension work inside JNPT holding yard | CR/DFCC | - | 12.5 |
| 21 | Construction of Helipad | PPA | 1.1 | |
| 22 | Remodeling Private siding at Ramco Cement | URC | - | 0.34 |
| 82.5 | 522.99 | |||
| B. Important Turn-key Works in Progress for Major Ports | |||
| Sl. No. | Name of Project | Client | Cost in Cr. |
| 1 | 3rd Line between Jasai and JNPT | JNPA | 126 |
| 2 | JNPT Development of DFC Compliant Common Rail Yard (CRY) with ROB Part I and modification works | JNPA | 330 |
| 3 | Rail Connectivity to Jalna Dry Port including construction of ROB | JNPA | 110.9 |
| 4 | Rail Connectivity to Wardha Dry Port | JNPA | 73 |
| 5 | Upgradation and modification of track in Kamarajar Port Ltd. | KPL | 33.52 |
| 6 | Augmentation / Doubling of Southern connectivity to KPL | KPL | 86.7 |
| 7 | Construction of ROB under Setu-Bharatam at Km 183+700 & Setu-Bharatam at Km 170+400 in the state of AP | MORTH | 188.7 |
| 8 | ROB at Km10+906 and ROB at Km 46+651 under Setu-Bharatam | MORTH | 155.7 |
| 9 | Construction of interchange-cum-ROB at Kutch Salt Jn in the state of Gujarat | DPA | 254.9 |
| 10 | Second exit road cum flyover at PPT as part of additional port connectivity from NH | PPA | 92.92 |
| 11 | Road Cum Flyover Crossing the BOT rail | PPA | 33.94 |
| tracks to have unobstructed access to the MCHP Areas | |||
| 12 | Rail upgradation work at Paradip Port Rail Yard | PPA | 15.46 |
| 13 | Maintenance of railway Track PPT siding from take-off point of Paradip Coaching yard including newly constructed BOT line (Total-84+30=114 Km) | PPA | 52.67 |
| 14 | Hiring of 6 locomotives and O&M | PPA | 61.69 |
| 15 | Fishing Harbour at Paradip | PPA | 99.75 |
| 16 | Project Development & Consultancy work for development of National Maritime Heritage Complex at Lothal, Gujarat | NMHC | 573.1 |
| 17 | S& T Maintenance work in KPL for three years | KPL | 7.96 |
| 18 | Partial upgradation of Track at Haldia | SMP | 13.2 |
| 19 | S& T Maintenance work in HDC | SMP | 22.16 |
| 20 | Inspection, Measurement, Correcting Parameters and Recouping deficient components of Railway Tracks under SMPK | SMP | 14.85 |
| 21 | Electrification of VPT Railway lines | VPA | 22.57 |
| 22 | Detailed Engineering and PMC for Modernization and Upgradation of Chennaii Fishing Harbour | ChPA | 81.05 |
| 23 | Fishing Harbour at VPA | VPA | 4 |
| 24 | Improvement of Railway tracks and rectification of 10degree curves | VPA | 16.8 |
| 25 | Upgradation of track in East Yard | VPA | 18.86 |
| 26 | Annual Track Maintenance work at VoCPA | VOCPA | 3.93 |
| 27 | Renewal and upgradation of Railway Track of Coal Yard at VOCPA | VOCPA | 0.36 |
| C. Important Consultancy for Major Ports (Completed/Ongoing) | ||||
| Sl. No. | Name of Project | Client | Services | |
| 1 | Heavy haul rail corridor from Ib Valley – Talcher to Paradip & Dhamra Port | PPA | Pre-feasibility Study | |
| 2 | Improve Line Capacity & Operational Flexibility | Feasibility Report | ||
| 3 | Barithengarh-Ratnagiri Rail Chord line | DPR, Bankability Report | ||
| 4 | Dedicated Port Rail connectivity for Salegaon to Paradip Port | DPR | ||
| 5 | Rail Master Plan for Paradip Port | DPR | ||
| 6 | Two ROBs at Paradip | DPR | ||
| 7 | FR & DPR Northern Rail Link Connecting to Kamarajar Port to Minjur / Ponneri | KPL | FSR & DPR | |
| 8 | Last mile connectivity to Enayam Port | VoCPA | FSR/ DPR | |
| 9 | Rail/Road connectivity to Kanyakumari Port | CoPA | FSR & DPR | |
| 10 | Rail-Road Connectivity to Belikeri & for Berth No. 17 in NMPT yard | NMPA | FSR | |
| 11 | Construction of new BG line between Indore Manmad | JNPA | DPR and FLS | |
| 12 | New line between Kandla-Jaisalmer | DPA | TEFR | |
| 13 | Rationalization of Rail Network for Mumbai Port Trust | MbPA | Study | |
| 14 | Estate Management in KoPT | KoPA | Estate Management | |
| 15 | Electrification, Signalling and additional line 1E in VPT Yard | VPA | DPR | |
| 16 | Study of increase of Rail Throughput in Vasco Castle Rock Section | MgPA | Study | |
| 17 | FSR for Development of Railway Network north of Oil Jetty No. 7 and near Jafrabadi for 1432 Acre (23km) | DPA | FSR | |
| 18 | Development of flyover bridge from Seahorse Junction to Dock Area of VPT | VPA | DPR | |
| 19 | Mechanization for handling of Bulk Cargo at Berths WQ7 and WQ8 | DPR | ||
| 20 | Conveyor from Western quay berth to Western Sector | TEFR | ||
| 21 | Extension of existing loop line by 750m in DPT yard for providing long haul loop. | DPA | DPR | |
| 22 | Preparation of DPR for construction of RCC drain & strengthening and widening of escape road in VOC PORT | VoCPA | DPR | |
| 23 | (i)Renewal of existing Diamond crossing with 60kg diamond crossing | ChPA | ||
| (ii) Direct entry from reception line, CONCOR line to Centre yard to avoid double handling and providing cross over connecting center yard- I & II at southern end of center yard | ||||
| (iii) Electrification of Railway lines as top wiring for engine on load concept at Western yard-I & II and full wiring to Center yard-II. | ||||
| 24 | FSR work for Flyover from Baikampady to KOICL junction | NMPT | FSR | |
| 25 | Electrification of Railway line of KPRK yard & GIM-Tuna section of DBTK | DPA | DPR | |
| D. Important Consultancy for Non-Major Ports & Other Major industries (Completed/Ongoing) | |||
| Sl. No. | Name of Project | Client | Services |
| 1 | Maintenance Work Vindhyanagar Plants | NTPC | Detailed Study Report |
| 2 | Rail Master Plan for Mundra Port | Adani Ports & SEZ | Study |
| 3 | Rail connectivity to Karanja Port | Mercantile Port Ltd | FSR |
| 4 | Development PFT with its rail connectivity at Erode | Legacy Warehouse | FSR |
| 5 | Rail connectivity to OPG TPP (DPR Completed) | GPIPL | DPR |
| 6 | Upgradation of Rail network for 4MTPA alumina plant near Lanjigarh | Vedanta Ltd, Lanjigarh | DPR & DE |
| 7 | Development of rail facilities to handle 6 MTPA of alumina traffic | Vedanta Ltd, Lanjigarh | FSR |
| 8 | Study on removal of infringements between Sanand and Khodiyar | CONCOR | Study |
| 9 | Rail connectivity to PFT in Nepal | JM Baxi | Study |
| 10 | Inspection of Bridge along the railway track of NTPC Rihand | NTPC | Technical Inspection |
| 11 | Enhancing evacuation of iron ore from Bacheli complex | NMDC | Pre-FSR |
| 12 | Operating Private Freight Terminal at RCF Siding (Trombay) | RCF | Traffic study |
| 13 | Assessment of Logistics Infrastructure at Vedanta Jharsuguda | Vedanta Ltd, JSG | Logistics Study |
| 14 | Rail infrastructure development at Sonepat for ICT&RIPL | JM Baxi | FSR |
| 15 | Rail Logistics study for Vedanta Lanjigarh and Jharsuguda Plant | Vedanta Ltd. | Logistics Study |
| 16 | Selection of routes for Khandband and Kalamanga iron ore mines to IR | Tata Steel Ltd | Traffic Study |
| 17 | Coal evacuation from Radhikapur West, Jamakhani and Kurloi North mines | Vedanta Ltd. | Logistics Study |
| 18 | Connection between new Rewari station of DFCCIL and Kishangarh Balawas to existing Gurgaon line of IR | DFCCIL | DPR |
| 19 | Rail connectivity to IMLH at Nangal Chaudhary (Haryana) | NICDC | DPR |
| 20 | Rail connectivity from for Ankola-Torangallu JSW steel plant | JSW Infra | Pre-FSR |
| 21 | Hazira Port rail connectivity – Essar Port Bulk Terminal | Essar | FSR |
| 22 | Development PFT with its rail connectivity at Erode | Legacy Warehouse | DPR |
| 23 | Construction of railway siding at Radhagaon Depot near Bokaro | BPCL | PMC |
| 24 | Rail connectivity to Dhamra Port | Dhamra Port | IE |
| 25 | Rail connectivity to IMLH at Nangal Chaudhary | NICDC | PMC |
| 26 | Rail connectivity to MMLH at Dadri | NICDC | DPR & PMC |
| 27 | Rail connectivity to Tamnar STPP of Jindal Power Ltd. | Jindal Power Ltd. | FSR |
| 28 | Coal Rail Logistics study for Chainpur, Jamadoba and Bhelatand (3 locations) | Tata Steel | FSR & DPR |
| 29 | FSR for rail connectivity to Paradip Depot | BPCL | FSR |
| 30 | S&T work Swarupganj and Dahej | CONCOR | PMC |
| 31 | Construction of railway siding for PEQCTPL | JSW-Paradip | DE & PMC |
| 32 | Rail & Road connectivity to Byepore and Kollam Port | Kerala Maritime Board | DPR |
| 33 | Yard Remodelling and Independent Engineer in the Ramco Cement | URC Construction | IE |
| 34 | Augmentation of Pipavav Port Rail Yard | Gujarat Pipavav Port | PMC |
| 35 | Rail connectivity to proposed bulk material handling yard at Paradip | Thriveni Earthmovers | TEFR |
| 36 | Proposed Rail Under Rail (RuR) facilities at Jharsuguda Plant | Vedanta Ltd. | FSR, DPR & DE |
| 37 | Coal evacuation from Jamakhani mines | Vedanta Ltd. | FSR |
| 38 | Private siding at Jharpada & Radhikapur West | Vedanta Ltd. | FSR & DPR |
| 39 | Preliminary Review of EXIM Cargo Evacuation & Rail & Road Connectivity issues at Navlaki, Porbandar, Bhavnagar and Okha. | GMB | FSR |
| 40 | Navigation Feasibility Study for Kalanchi-Khedapada (25Km approx.) and Bansjhari- Mallikpur- Hemnagar Stretch (80Km approx.) of NW 44 including Traffic study and bathymetry survey: - (Ichamati River) | IWAI | FSR |
| 41 | Preparation of FSR, DPR and PMC of the proposed Tourist-cum-Cargo Inland Water Transport (IWT) Terminal of IWAI at Bogibeel, Assam. | IWAI | FSR, DPR & PMC |
| E. Consultancy for CIL subsidiaries (Completed/Ongoing) | ||||
| Sl. No. | Name of Project | Services provided by IPRCL | Subsidiary Name | Approx. Project Cost (In Rs. Cr.) |
| 1 | Development of Rail infrastructure required for Sanghamitra OCP (20/27 MTPA) | FSR & DPR & PMC | CCL | 300.08 |
| 2 | Railway for construction of new line/modification of existing rail lines by keeping provisioning for Silo Loading System for Konar | FSR & DPR | CCL | 64.33 |
| 3 | Railway for construction of new line/modification of existing rail lines by keeping provisioning for Silo Loading System at Karo | FSR & DPR & PMC | CCL | 136.8 |
| 4 | Construction of new line/ modification of existing rail lines by keeping provisioning for Rapid Loading System for New Kathara Washery | FSR & DPR | CCL | 20.78 |
| 5 | construction of new line/ modification of existing rail lines at Kuju Siding by keeping provisioning for Rapid Loading System for Topa Washery | FSR & DPR | CCL | 37.46 |
| 6 | Routine Maintenance work of Piparwar- McCluskieganj surface Rail line of CCL (28.78 ETKM) | Track Maintenance | CCL | 23.69 |
| 7 | New Railway Siding with Rail Connectivity at Itapara under Salanpur Area | FSR & DPR | ECL | 155 |
| 8 | Development of rapid coal loading siding at Amalgamated Yekona I & II OCM of Majri Area | FSR , DPR & PMC | WCL | 68.43 |
| 9 | Construction of New Railway Siding upto Batura opencast Project | DPR & Geophysical Survey | SECL | 110.69 |
| 10 | New rail connectivity from Sardega to Pelma | TEFR | MCL | 1389 |
| 11 | Railway Siding at Lajkura | PMC | MCL | 75.7 |
| 12 | Upgradation of Surakachar railway siding | CTR | SECL | 6.96 |
| 13 | Railway siding at Manikpur CHP | DE & PMC | SECL | 111.65 |
| 14 | Railway siding at Baroud OCP | DE & PMC | SECL | 141.44 |
| 15 | CTR and other improvement works (7.3ETKM) for Railway track of Dipka Siding | CTR | SECL | 23.39 |
| 16 | CTR work of Junadih siding of SECL | CTR | SECL | 45.01 |
| 17 | Railway Siding for New Rapid Loading System at Dinesh OCP, Makardokra | FSR, DPR, DE & PMC | WCL | 127 |
| 18 | OHE work at Block-B to Madheiya Railway station with SILO | FSR, DPR & PMC | NCL | 10 |
| 19 | Development of railway siding of Jhingurda Siding | DPR & PMC | NCL | 42.94 |
| 20 | Comprehensive Rail Track Maintenance of existing Railway Siding of NCL for 3yr. | Track Maintenance | NCL | 33.41 |
| F. Consultancy assignments for Ropeways - Completed | |||||
| Sl. No. | Project and location | Length and type of Ropeway | Client | Standard | Approx. Cost (Crores) |
| 1 | Tamil Nadu - Kanyakumari Ropeway and Marine Bridge | 700 m | TNMB | CEN | 115 |
| 2 | Cheiraoching – Marjing Ching | 6.0 Km | Govt. of Manipur | CEN | 340 |
| 3 | Sendra To Thanga (Loktak) | 4.7 Km | CEN | 265 | |
| 4 | Andhra Pradesh – Berm Park To Bhavani Island | 700 m | Govt. of A.P. | CEN | 80 |
| BIS | 25 | ||||
| 5 | Anandpur Sahib - Naina Devi Ropeway Project | 3.85 Km | Govt of H.P and Punjab | CEN | 280 |
| 6 | Maharashtra- Nanduri – Saptashrungi- Ropeway | 3.10 Km | CEN | 132 | |
| BIS | 95 | ||||
| 7 | Maharashtra- Saptashrungi- Markendaya Ropeway | 2.00 Km | Govt. of Maharashtra | CEN | 80 |
| BIS | 46 | ||||
| 8 | Maharashtra-Saptashrungi- Markendaya- Hattigaon Ropeway | 13.8 Km | CEN | 586 | |
| 9 | Maharashtra- Hatti – Dhodap Fort | 2.4 Km | CEN | 88 | |
| BIS | 56 | ||||
| 10 | Himachal Pradesh- Narkanda - Hatu Peak | 4.0 Km | Govt of H.P | CEN | 170 |
| 11 | Udaipur Station- Matabari Temple | 1.6 Km | Govt. of Tripura | CEN | 140 |
| BIS | 80 | ||||
| 12 | Tripura : Maharani- Chabimura | 5.9 Km | BIS | 135 | |
| 13 | MMRDA: Charkop - Marve Urban Ropeway Project | 3.6 Km | MMRDA | CEN | 383 |
| 14 | MMRDA: Mahavirnagar – Gorai Urban Ropeway Project | 7.20 Km | CEN | 575 | |
| 15 | Madhya Pradesh: Preliminary Assessment Report for 12 locations in Madhya Pradesh | 24 Km | MPTB | BIS | 250 |
| 16 | Mumbai- Elephanta Ropeway. | 8 Km | MbPT | CEN | 700 |
| 17 | Madhya Pradesh: Jatashankar Mahadev Ropeway Project | 470 m | MPSTDCL | BIS | 13 |
| 18 | Gujarat: SSNNL Ropeway project near Statue of Unity | 1.25 Km | SSNNL | CEN | 62 |
| 19 | Meghalaya: Shillong Peak | 930 m | MIDFC, Govt. of Meghalaya | CEN | 78 |
| BIS | 43 | ||||
| 20 | Meghalaya: Umiam Lake viewpoint to Umiam water sport Complex | 800 m | CEN | 58 | |
| BIS | 44 | ||||
| 21 | Meghalaya: Tura Peak | 3.15 Km | CEN | 140 | |
| BIS | 60 | ||||
| 22 | Uttarakhand - Dehradun City Urban Ropeway Project | 25 Km | DMRC | CEN | 1000 |
| 23 | Uttarakhand - Rishikesh – Neelkanth Mahadeo Temple | 6 KM | UKMRC | BIS | 300 |
| 24 | Preparation of DPR for Neelkanth Ropeway Project | UKMRC | Uttarakhand | - | 353 |
| 25 | MMRDA: Mahavirnagar – Gorai Urban Ropeway Project | 7.20 Km | MMRDA | CEN | 575 |
| 26 | Mumbai- Elephanta Ropeway. | 8 Km | MbPT | CEN | 700 |
| 27 | Gujarat: SSNNL Ropeway project near Statue of Unity | 1.25 Km | SSNNL | CEN | 62 |
| 28 | Bid Process Management for Jatashankar Ropeway Project | MPSTDCL | Madhya Pradesh | - | |
| 29 | Preparation of DPR for Nandi Hill Ropeway Project | iDeCK | Karnataka | - | 150 |
| 30 | Preparation of DPR for Dehradun City Ropeway Project | DMRC | Uttarakhand | ||
| 31 | Bid Process Management for Mahavirnagar to Gorai Ropeway Project | MMRDA | Maharashtra | - | - |
| Consultancy assignments for Ropeways - Ongoing | ||||
| Sr. No. | Name of the Project | Client | State | Approx. project Cost (Cr.) |
| 1 | Preparation of DPR and Bid Process Management for Shri Ekvira Ropeway Project | DOT, Maharashtra | Maharashtra | 45 |
| 2 | Film City to Jewer Airport PRT Project | YEIDA, U.P. | ||
| 3 | Preparation of DPR and Bid Process Management for Bhojpur Ropeway Project | MPTB | Madhya Pradesh | 10 |
| 4 | Preparation of DPR and Bid Process Management for Omkareshwer Ropeway Project | MPTB | Madhya Pradesh | 15 |
| 5 | Preparation of DPR and Bid Process Management for Salkanpur Ropeway Project | MPTB | Madhya Pradesh | 40 |
| 6 | Preparation of DPR for Kodachadri Hill Ropeway Project | iDeCK | Karnataka | 165 |
| 7 | Preparation of DPR and Bid Process Management for Kachiguda-MGBS-Zoological Ropeway Project | HUMTA | Telangana | 500 |
| 8 | Preparation of DPR and Bid Process Management for Assembly-Khairatabad-Paradise PRT System | HUMTA | Telangana | 600 |
| 9 | Preparation of DPR and Bid Process Management for Raigiri – Proposed Bus Stand(Yadagirigutta) PRT Project | HUMTA | Telangana | 420 |
| 10 | Preparation of DPR and Bid Process Management for Film City to Jewer Airport PRT Project | YEIDA | Uttar Pradesh | 810 |